May 04: Architect comes to discuss kitchen plans.
Discovery that GC was building based on wrong set of plans!
May 05: Resolved construction plans with city.
May 12: Survey done by third party to determine property lines.
May 19: Foundation inspection failed.
May 24: Foundation inspection passed! Concrete poured.
May 25/26: Work on rough plumbing starts.
May 30: Memorial Day! Our GC would've worked if it had not been for city code that prevents construction on holidays. :p